To achieve its goals efficiently, the PURSUE project is structured into a series of thematic Work Packages (WPs). Each WP is led by a partner institution and focuses on specific aspects of project implementation—ranging from initial setup and curriculum development to training, dissemination, and quality assurance.

Below is a breakdown of the Work Packages, their respective leaders, timelines, and associated tasks:

Work Package Leader Task
WP1- Project Initial Activities Dar Es Salam Institute of Technology (P5) Task 1.1 – Initial Workshop
Task 1.2 – Setting Grant Agreement with Participants
Task 1.3 – Initial Conference of Project Participants, Kick-Off meeting
WP2- Course Development Mogadishu University (P8) Task 2.1 – Benchmarking the traditional and conventional approaches
Task 2.2 – Material development for courses
Task 2.3 – Material development for the traineeship
WP3- Laboratory Capacity Enrichment Eduardo Mondlane University (P3) Task 3.1 – Equipment Purchasing
      T3.1-A Baseline condition of the laboratory
      T3.1-B Feasibility Report for New Equipments
      T3.1.C Equipment Purchasing
Task 3.2 – Traineeship for equipment academics
Task 3.3 – Traineeship for equipment for technicians
Task 3.4 – Traineeship for equipment for student
WP4- Implementation of Teaching Courses and Training Modules Ardhi University(P6) Task 4.1 -Traineeship program development
Task 4.2 – Application of the traineeship
Task 4.3 – Student projects (IP)
Task 4.4 – Translation of the traineeship program
Task 4.5 – Face-to-face training
WP5- Quality Assurance University of Porto (P2) Task 5.1 – Quality Assurance Framework Development
Task 5.2 – Inter-university & Cross- university Assessment Internal Assessment by
Task 5.3 – Implementation of Quality Assurance Measures
Task 5.4 – Continuous Monitoring and Evaluation
Task 5.5 – Stakeholder Feedback Mechanism
WP6- Dissemination and Exploitation of the Project Results Simad University (P7) Task 6.1 – Project Web-site & PC Universities Websites:
Task 6.2 – Project Publications on project open access platform, Project Quality Control & Monitoring Plan
Task 6.3 – Project Public Events
Task 6.4 – Stakeholders Events
Task 6.5 – Short-term online and face-to-face professional Advanced Training
WP7- Project Management and Coordination Sakarya University (P1) Task 7.1 – Contractual Issues and Project Progress Reports
Task 7.2 – Elaboration and Dissemination of the Practical Project Management Guide (PPMG)
Task 7.3 – Project Progress Reports Coordination Meetings of the Project partners
Task 7.4 – Day-to-day administration of the Project and monitoring of the Project activities